4 Mead Street, Avondale, Auckland
Estimated Settlement Date October 2024
Homes completed October 2024
Work completed September 2024
External cladding and painting completed
Landscaping fencing and final inspections progressing for project handover in October
Work completed August 2024
GIB linings complete
External cladding and painting in progress
Kitchen and tile installation commenced
Work completed July 2024
Framing complete
Roof and window installation complete
GIB lining commencing
Work completed June 2024
Ground and first floor framing complete
Prepping for roofing to commence
Work completed May 2024
Foundations complete
Driveway poured
Ground floor framing underway
Work completed April 2024
Earthworks complete
Drainage and under-slab plumbing underway
Work completed March 2024
Demo complete
Earthworks ready to commence