Build Update
4 Mead Street, Avondale, Auckland

Estimated Settlement Date October 2024


Homes completed October 2024


Work completed September 2024

  • External cladding and painting completed

  • Landscaping fencing and final inspections progressing for project handover in October


Work completed August 2024

  • GIB linings complete

  • External cladding and painting in progress

  • Kitchen and tile installation commenced


Work completed July 2024

  • Framing complete

  • Roof and window installation complete

  • GIB lining commencing


Work completed June 2024

  • Ground and first floor framing complete

  • Prepping for roofing to commence


Work completed May 2024

  • Foundations complete 

  • Driveway poured

  • Ground floor framing underway 


Work completed April 2024

  • Earthworks complete 

  • Drainage and under-slab plumbing underway 


Work completed March 2024

  • Demo complete

  • Earthworks ready to commence