Build Update
48 Torrington Crescent, Glen Innes, Auckland

Estimated Settlement Date May 2025


Work completed January 2025

  • Roofing and windows installed

  • Services and insulation installed ready for GIB


Work completed December 2024

  • Ground and first floor framing complete

  • Driveway complete

  • Preparing for roofing and window installation


Work completed November 2024

  • Foundations complete

  • Framing progressing for roof

  • Driveway forming underway


Work completed October 2024

  • Demolition, civils, retaining and drainage completed

  • Slabs underway