Build Update
48 Torrington Crescent, Glen Innes, Auckland
Estimated Settlement Date May 2025
Work completed January 2025
Roofing and windows installed
Services and insulation installed ready for GIB
Work completed December 2024
Ground and first floor framing complete
Driveway complete
Preparing for roofing and window installation
Work completed November 2024
Foundations complete
Framing progressing for roof
Driveway forming underway
Work completed October 2024
Demolition, civils, retaining and drainage completed
Slabs underway