Homes completed July 2023


Work completed June 2023

  • Fence staining and landscaping in progress

  • Patios poured


Work completed May 2023

  • Internal work close to completion

  • Patios soon to be poured

  • Fencing and landscaping set to begin


Work completed April 2023

  • Cladding and Internal fit out is progressing well as we prepare the project for kitchen and bathroom fit out in the coming weeks


Work completed March 2023

  • Units are weathertight

  • Cladding is in progress

  • Gib is on site and pre-line inspections are underway ready for linings


Work completed February 2023

  • Framing completed

  • Roofing and window install in progress

  • Cladding materials on site

  • Services 1st fix progressing in preparation for internal linings


Work completed January 2023

  • Ground floor frames and midfloor are completed

  • Trusses are on site ready for isntall

  • Roof and window procurement are underway


Work completed November/December 2022

  • Frames are on site and underway

  • External surfacing and driveways are completed

  • Council approvals for titles progressing


Work completed October 2022

  • Completion of drainage

  • Driveway completion

  • Underlslab plumbing in preparation for slab pours