Build Update
52 Rutland Road, Mount Wellington, Auckland
Estimated Settlement Date August 2023
Homes completed July 2023
Work completed June 2023
Fence staining and landscaping in progress
Patios poured
Work completed May 2023
Internal work close to completion
Patios soon to be poured
Fencing and landscaping set to begin
Work completed April 2023
Cladding and Internal fit out is progressing well as we prepare the project for kitchen and bathroom fit out in the coming weeks
Work completed March 2023
Units are weathertight
Cladding is in progress
Gib is on site and pre-line inspections are underway ready for linings
Work completed February 2023
Framing completed
Roofing and window install in progress
Cladding materials on site
Services 1st fix progressing in preparation for internal linings
Work completed January 2023
Ground floor frames and midfloor are completed
Trusses are on site ready for isntall
Roof and window procurement are underway
Work completed November/December 2022
Frames are on site and underway
External surfacing and driveways are completed
Council approvals for titles progressing
Work completed October 2022
Completion of drainage
Driveway completion
Underlslab plumbing in preparation for slab pours