Build Update
2 Riversdale Road, Avondale, Auckland
Estimated Settlement Date March 2024
Work completed February 2024
Work completed January 2024
Landscaping, fencing and finishing touches underway
Work completed December 2023
Titling kitchens and flooring nearing completion
Exterior cladding completed and scaffold removed
Work completed November 2023
Internal paint underway
External cladding nearing completion
Work completed October 2023
Building weather-tight
Cladding and GIB underway
Work completed August/September 2023
Framing nearing completion
Roofing and windows to follow
Work completed July 2023
Slabs complete
Driveway being poured
Work completed June 2023
Earthworks and drainage completed
Slab preparation in progress