Build Update
2 Riversdale Road, Avondale, Auckland

Estimated Settlement Date March 2024


Work completed February 2024


Work completed January 2024

  • Landscaping, fencing and finishing touches underway


Work completed December 2023

  • Titling kitchens and flooring nearing completion

  • Exterior cladding completed and scaffold removed


Work completed November 2023

  • Internal paint underway

  • External cladding nearing completion


Work completed October 2023

  • Building weather-tight

  • Cladding and GIB underway 


Work completed August/September 2023

  • Framing nearing completion

  • Roofing and windows to follow


Work completed July 2023

  • Slabs complete

  • Driveway being poured


Work completed June 2023

  • Earthworks and drainage completed

  • Slab preparation in progress