Build Update
39 Pakuranga Road, Pakuranga, Auckland
Estimated Settlement Date September 2024
Homes completed September 2024
Work completed August 2024
Council final inspection landscaping and interior clean progressing for Settlement in September
Work completed July 2024
Cladding 90% complete
Internal fit out 50% complete
Kitchen and bathroom installation progressing
Work completed June 2024
Roofing and windows complete
Internal lining and cladding underway
Work completed May 2024
Ground and first-floor framing complete
Roofing is in progress and window installations underway
Work completed April 2024
Slabs complete
Driveway and paths poured
Ground and first-floor framing in progress
Work completed March 2024
Drainage complete
Earthworks and utilities completed
Under slab plumbing and foundations underway
Work completed February 2024
Demo complete
Earthworks in progress