Build Update
39 Pakuranga Road, Pakuranga, Auckland

Estimated Settlement Date September 2024


Homes completed September 2024


Work completed August 2024

  • Council final inspection landscaping and interior clean progressing for Settlement in September


Work completed July 2024

  • Cladding 90% complete

  • Internal fit out 50% complete

  • Kitchen and bathroom installation progressing


Work completed June 2024

  • Roofing and windows complete

  • Internal lining and cladding underway


Work completed May 2024

  • Ground and first-floor framing complete

  • Roofing is in progress and window installations underway


Work completed April 2024

  • Slabs complete

  • Driveway and paths poured

  • Ground and first-floor framing in progress 


Work completed March 2024

  • Drainage complete

  • Earthworks and utilities completed

  • Under slab plumbing and foundations underway


Work completed February 2024

  • Demo complete

  • Earthworks in progress