Build Update
1 Frank Grey Place, Otahuhu, Auckland

Estimated Settlement Date March 2024


Homes completed March 2024


Work completed January 2024

  • Exterior cladding completed and scaffold removed

  • Bathrooms and kitchens underway  

  • Landscaping and fencing commenced  


Work completed December 2023

  • Buildings weathertight  

  • Cladding progressing

  • Units lined and stop ready for paint


Work completed November 2023

  • Roofs installed

  • Windows installed

  • Serviced install ready for linings


Work completed October 2023

  • Slabs completed

  • Preparing framing for roofing


Work completed August/September 2023

  • Drainage completed

  • Services installed

  • Slab pour imminent


Work completed July 2023

  • Demo complete

  • Earthworks in progress