Build Update
191 England Street, Linwood, Christchurch

Completion Date January 2023


Completed January 2023


Work completed November/December 2022

  • Cladding finished around entry doors

  • Plumbers 95% complete 

  • Electrical 95% complete 

  • Range hoods installed

  • Carpet layers finishing of stairs


Work completed October 2022

  • Painters have all bathroom and kitchens ready

  • Kitchens are being installed

  • Builders still working on cladding

  • Installed all iron cladding last week/ waiting on flashings to finish

  • Tilers started


Work completed September 2022

  • Doors currently getting installed

  • Brick layers up half way

  • Cavity battens on for pre clad inspection

  • Gib fixers are 85% complete

  • Gib stops have made a start on units 1,2,3,4 and waiting on inspection for 5-8 to proceed

  • Pushing to have painter done and out by 25th


Work completed August 2022

  • Civil works complete

  • Framing complete

  • Roof complete

  • Close-in commenced


Work completed July 2022

  • Foundations complete

  • Civil works and services complete

  • Framing commenced