Build Update
191 England Street, Linwood, Christchurch
Completion Date January 2023
Completed January 2023
Work completed November/December 2022
Cladding finished around entry doors
Plumbers 95% complete
Electrical 95% complete
Range hoods installed
Carpet layers finishing of stairs
Work completed October 2022
Painters have all bathroom and kitchens ready
Kitchens are being installed
Builders still working on cladding
Installed all iron cladding last week/ waiting on flashings to finish
Tilers started
Work completed September 2022
Doors currently getting installed
Brick layers up half way
Cavity battens on for pre clad inspection
Gib fixers are 85% complete
Gib stops have made a start on units 1,2,3,4 and waiting on inspection for 5-8 to proceed
Pushing to have painter done and out by 25th
Work completed August 2022
Civil works complete
Framing complete
Roof complete
Close-in commenced
Work completed July 2022
Foundations complete
Civil works and services complete
Framing commenced