Build Update
12 Edward Avenue, Edgeware, Christchurch

Estimated Settlement Date April 2023


Homes completed April 2023


Work completed March 2023

  • Concrete paths and patios booked to pour on the 11th

  • Plumbers fit off completed 

  • Builder fit off completed 

  • Electrical fit off almost complete

  • Retaining wall complete 

  • Currently working on fencing 60% complete  


Work completed February 2023

  • Cladding 98% complete

  • Kitchen install started

  • Painters finished 5 units 

  • Exterior paid due to completed in weeks time 


Work completed January 2023

  • Gib stopper have started

  • Brick layers started

  • Weathertex started going up


Work completed November/December 2022

  • Plumbers on-site doing pre pipe

  • Sparkys on-site doing pre wire

  • Builders straighting and installing ceiling battens and blocking

  • Pre line inspection booked for 20th


Work completed October 2022

  • Drive way about to be poured

  • Roof install this week on back units

  • Currently wrapping the buildings

  • Facia and gutter installed


Work completed September 2022

  • First floor frames stood and currently bracing them up

  • Trusses turned up on site

  • Driveway to carry on construction early next month


Work completed August 2022

  • Foundations complete

  • Inground services complete

  • Framing commenced