Build Update
12 Edward Avenue, Edgeware, Christchurch
Estimated Settlement Date April 2023
Homes completed April 2023
Work completed March 2023
Concrete paths and patios booked to pour on the 11th
Plumbers fit off completed
Builder fit off completed
Electrical fit off almost complete
Retaining wall complete
Currently working on fencing 60% complete
Work completed February 2023
Cladding 98% complete
Kitchen install started
Painters finished 5 units
Exterior paid due to completed in weeks time
Work completed January 2023
Gib stopper have started
Brick layers started
Weathertex started going up
Work completed November/December 2022
Plumbers on-site doing pre pipe
Sparkys on-site doing pre wire
Builders straighting and installing ceiling battens and blocking
Pre line inspection booked for 20th
Work completed October 2022
Drive way about to be poured
Roof install this week on back units
Currently wrapping the buildings
Facia and gutter installed
Work completed September 2022
First floor frames stood and currently bracing them up
Trusses turned up on site
Driveway to carry on construction early next month
Work completed August 2022
Foundations complete
Inground services complete
Framing commenced