Build Update
33 Convoy Lane, Otahuhu, Auckland
Estimated Settlement Date April 2025
Work completed January 2024
Roof & windows installed
Gib installed
Cladding progressing
Work completed December 2024
Ground and first floor framing complete
Roof and window installation nearing completion
Work completed November 2024
Foundations complete
Framing progressing for roof
Work completed October 2024
Demolition, civils, retaining and drainage completed
Slabs underway