Build Update
35 Convoy Lane, Otahuhu, Auckland
Estimated Settlement Date April 2023
Homes completed April 2023
Work completed March 2023
CCC was received ahead of schedule in March
All purchasers have carried out inspections ready for settlement in early April
Work completed February 2023
Units practically complete
Landscaping and fencing works nearing completion
CCC inspections underway
Work completed January 2023
Scaffolds are coming down ready for landscaping and fencing to commence
Internal painting is nearing completion
Kitchens and bathrooms are progressing well
Flooring and electrical fit off are underway
Work completed November/December 2022
Buildings are weathertight
Gib is being installed
Exterior cladding and painting progressing
Work completed October 2022
Roofing and window installation coming to completion
Cladding installation
Service installation and insulation in preparation for Gib install
Work completed September 2022
First floor framing complete
Roof truss install 50% complete
Roofing fabrication underway
Windows on site ready for install
Work completed August 2022
Earthworks and drainage complete
Foundation slabs complete
Framing commenced
Work completed July 2022
Earthworks complete
Foundations complete
Drainage commenced
Pre-nail shop drawings complete