Build Update
35 Convoy Lane,
Otahuhu, Auckland

Estimated Settlement Date April 2023


Homes completed April 2023


Work completed March 2023

  • CCC was received ahead of schedule in March

  • All purchasers have carried out inspections ready for settlement in early April


Work completed February 2023

  • Units practically complete

  • Landscaping and fencing works nearing completion

  • CCC inspections underway


Work completed January 2023

  • Scaffolds are coming down ready for landscaping and fencing to commence

  • Internal painting is nearing completion

  • Kitchens and bathrooms are progressing well

  • Flooring and electrical fit off are underway


Work completed November/December 2022

  • Buildings are weathertight

  • Gib is being installed

  • Exterior cladding and painting progressing


Work completed October 2022

  • Roofing and window installation coming to completion

  • Cladding installation

  • Service installation and insulation in preparation for Gib install


Work completed September 2022

  • First floor framing complete

  • Roof truss install 50% complete

  • Roofing fabrication underway

  • Windows on site ready for install


Work completed August 2022

  • Earthworks and drainage complete

  • Foundation slabs complete

  • Framing commenced


Work completed July 2022

  • Earthworks complete

  • Foundations complete

  • Drainage commenced

  • Pre-nail shop drawings complete