Build Update
29 Bolton Avenue, Spreydon, Christchurch
Completion Date October 2022
Homes completed October 2022
Work completed September 2022
Final paint touch-us
Landscaping underway
Work completed August 2022
New titles
Cladding 95% complete
Interior linings complete
Interior fit out commenced
Work completed July 2022
Framing complete
Civil works and services complete
Cladding commenced
Interior lining commenced