Build Update
54 Barrack Road, Mount Wellington, Auckland

Estimated Settlement Date December 2024


Work completed September 2024

  • Scaffolding down

  • External cladding and painting completed

  • GIB lining completed with painting and interior fit outs in progress

  • Landscaping work commenced


Work completed August 2024

  • Homes weathertight with roofs and windows complete

  • GIB internal linings underway

  • External cladding and painting progressing  


Work completed July 2024

  • Framing completed

  • Roof and window install commencing


Work completed June 2024

  • Ground floor framing complete

  • First floor framing in progress


Work completed May 2024

  • Retaining and draining complete

  • Foundations complete


Work completed April 2024

  • Earthworks complete

  • Retaining and draining underway


Work completed March 2024

  • Demo complete

  • Earthworks ready to commence