Build Update
54 Barrack Road, Mount Wellington, Auckland
Estimated Settlement Date December 2024
Work completed September 2024
Scaffolding down
External cladding and painting completed
GIB lining completed with painting and interior fit outs in progress
Landscaping work commenced
Work completed August 2024
Homes weathertight with roofs and windows complete
GIB internal linings underway
External cladding and painting progressing
Work completed July 2024
Framing completed
Roof and window install commencing
Work completed June 2024
Ground floor framing complete
First floor framing in progress
Work completed May 2024
Retaining and draining complete
Foundations complete
Work completed April 2024
Earthworks complete
Retaining and draining underway
Work completed March 2024
Demo complete
Earthworks ready to commence