Build Update
12 Allen Road, Mount Wellington, Auckland

Estimated Settlement Date December 2023


Homes completed November 2023


Work completed October 2023

  • Cladding install nearing completion

  • Internal fitout underway


Work completed August/September 2023

  • Cladding underway

  • Lining completed

  • Gib stopping underway


Work completed July 2023

  • Frames complete

  • Roofs and wrap commencing


Work completed June 2023

  • Slabs recently poured

  • Framing in progress


Work completed May 2023

  • Earthworks in progress