Build Update
71 Ruawai Road, Mt Wellington, Auckland

Completion Date December 2022


Homes completed December 2022


Work completed October 2022

  • Final Paint touch-us

  • Flooring completion

  • Landscaping underway


Work completed September 2022

  • Scaffold removal underway

  • External painting nearing completion for scaffold to come down

  • Internal painting completed

  • Kitchen, tiling and flooring installs underway


Work completed August 2022

  • Weathertight

  • Cladding underway

  • Gib commenced

  • Driveway complete


Work completed July 2022

  • Framing complete

  • Trusses 60% complete

  • Roof 20% complete

  • Windows onsite, installation has commenced