Build Update
71 Ruawai Road, Mt Wellington, Auckland
Completion Date December 2022
Homes completed December 2022
Work completed October 2022
Final Paint touch-us
Flooring completion
Landscaping underway
Work completed September 2022
Scaffold removal underway
External painting nearing completion for scaffold to come down
Internal painting completed
Kitchen, tiling and flooring installs underway
Work completed August 2022
Weathertight
Cladding underway
Gib commenced
Driveway complete
Work completed July 2022
Framing complete
Trusses 60% complete
Roof 20% complete
Windows onsite, installation has commenced